Back in 2012, Paul Surin, IBM’s global lead on the Built Environment and BIM, thought he was moving into a highly energy-efficient new-build, but the reality could not have been more different. In a conversation with environmental performance assessors SHIFT, Paul lays bare just how bad his housing nightmare became
We bought the property in February 2012. The house was expected to be a high-standard home, built at an EPC B rating, including 6m2 of solar thermal panels. Unfortunately, the reality was different.
From day one we had a lot of problems. While the agent was handing over our new dream house, I discovered there was no water in the heating system, the solar thermal cylinder was empty, there were missing door handles, there was no grass, and incomplete work on the house surroundings.
It was a nightmare. It had taken over three months for developer to complete the basic work on the home. While they were doing this, they found more issues and had to replace the solar pump system as there was no solar fluid and the pump burnt out.
Over time, we discovered our energy bills were nowhere near the suggested EPC figures. I am aware the EPC figures are not accurate, but still, we did not expect to have to pay £1,200 per year on energy bills for such a modern house
“It was only a matter of the time before the cylinder dropped through our ceiling – which had been an issue in our neighbours’ homes”
I started digging into the specification, insulation standards, and construction details of the house. It was very clear that there were more issues. In the attic roof space, the insulation was poorly applied, and I even discovered packed rolls being left in there. There was no insulation between the rafters, in the cavity, behind the electric cupboard.
I had been arguing with the developer for over three-and-a-half years till they finally accepted the liability. I eventually reported them to NHBC, although it took a while for them to accept my claim. Despite the setbacks, I was determined to win this battle. I had a thermal survey done, involved our local councillor, and appealed the NHBC decision.
Finally, by the end of 2015, the NHBC had accepted my claim and forced the developer to rectify the issues. The rectification work itself had taken several months to complete, and I had to do all the inspection work on my own.
Throughout this rectification work, more issues arose. The 300-litre cylinders fitted in the first-floor airing cupboard were not effectively supported. One stainless steel cylinder was resting on two small timbers and a plywood. The plywood was already cracked, so it was only a matter of the time before the cylinder dropped through our ceiling – which had been an issue in our neighbours’ homes.
Our front door had started cracking and, after about a year, we were unable to lock or even close the door. The developer needed to realign, fill in cracks, and repaint the door. This took longer than expected.
So, five years after purchasing the property, I finally had the house I expected back in 2012. I did end up receiving compensation from the developer for the excess in energy bills costs. Right now, the property costs us around £500-600 per year to run.
Paul Surin is a chartered member and engineer of both the Institute of Engineering and Technology and the Chartered Institute of Building. He is a member of Built Environment Executive at the IET, vice-chair of BIM4HOUSING, and a co-opted UK expert at European Standardisation Working Group for BIM – CEN TC 442 and ISO.
He is also chair of the Construction Product Europe Digitalization Task Group.