Retrofit programmes are not always straightforward. Labour shortages, fragmented supply chains and the practicalities of upgrading homes can make them complex and difficult to deliver at scale.
For Fairhive, the experience of the Warm Homes: Social Housing Fund (WH:SHF) Wave 3 programme – previously known as the Social Housing Decarbonisation Fund – has demonstrated that some of the biggest gains come before work even begins, through early market engagement and building the right delivery team around the programme.
Managing approximately 9,000 homes across Buckinghamshire, Hertfordshire, Bedfordshire, Berkshire and surrounding areas, Fairhive set out to deliver retrofit improvements to 550 properties across its stock through WH:SHF Wave 3. Following additional funding, that target increased to 800 properties.
The programme covered a broad range of measures, including insulation, air source heat pumps, solar PV, energy storage, and ventilation upgrades. Delivering these across Aylesbury and several rural villages brought another layer of logistical challenges.
Going to market early
Building on lessons from Wave 2, Fairhive entered Wave 3 with a clear understanding of what needed to be delivered and where, shaping both delivery strategy and procurement approach from the outset.
One of Fairhive’s biggest strategic decisions was going to market before exact funding had been confirmed.
Using the Procure Plus Retrofit Dynamic Purchasing System, contractors were given greater visibility of the opportunity and more time to prepare for delivery ahead of funding confirmation, while Fairhive was protected by the proviso that no work was guaranteed until funding was in place. This helped avoid losing valuable delivery time.
Detailed tender documentation also gave contractors the confidence to price and plan accurately, resulting in a strong market response of 14 bids from a mix of national installers and local SMEs.
A staggered but parallel tender for the Retrofit Assessor, Retrofit Designer and Health and Safety Consultant roles meant all appointments landed within a similar timeframe, putting the programme in a strong position from day one: a fully procured project team, clear visibility of Year 1 properties and measures, and residents prepared for installation.
A team built for delivery
Fairhive’s in-house Sustainability Team has grown alongside the programme, now including two Retrofit Coordinators, a Project Manager, a Contract Manager, two Resident Liaison Officers and administrative support.
Rather than seeking a turnkey solution, Fairhive chose to work with Tier 2 contractors and build internal capacity. This helped to support SMEs, control costs, and improve pace and quality of delivery.
This investment extends beyond the retrofit programme itself, as new roles and training within the Direct Labour Organisation mean ongoing maintenance of new kit can now be managed in-house too. This has helped build organisational capacity that will continue to deliver long after the programme ends.
The results, one year in
Year 1 deliberately focused on rural locations and villages, with the installer moving efficiently from area to area. Weekly project meetings kept all parties aligned, while Procure Plus’ in-house digital management platform Schemes Plus gave the team real-time visibility of progress and spend throughout delivery.
By the end of Year 1, the programme had:
- Completed 150 properties
- Installed 144 solar panels
- Installed 78 heat pumps
- Added 123 insulation measures
- Supported seven people into employment, including individuals affected by homelessness, care leavers, and ex-offenders, via referral partners including Oasis Partnership and Smart Works Reading
Fairhive also used the programme to build wider community value, committing to ongoing donations and volunteering with local wildlife charities, and giving colleagues upskilling opportunities in renewables through its principal contractors.
Why it worked
Fairhive puts the programme’s success down to a combination of factors: the decision to go to market early; detailed upfront planning that gave contractors pricing confidence; the strength of the internal team; effective collaboration with delivery partners; the flexibility to adapt as requirements evolved; and real-time visibility of progress and spend.
Cecily Church, Head of Sustainability at Fairhive, said: “Going to market before funding was confirmed felt like a risk, but it gave our contractors and us the head start we needed to hit the ground running. Twelve months on, we’ve not only met our Year 1 targets, we’ve also secured funding to keep the momentum going into Year 2.”
Together, these factors have enabled Fairhive to successfully deliver Year 1 and build a strong foundation for Year 2, now underway following the award of additional funding.


Ongoing partnership with Procure Plus
Unlike previous contracts, where framework providers were typically involved only at the procurement stage, Fairhive has maintained an ongoing relationship with Procure Plus throughout delivery.
Procure Plus acted as a mediator in discussions, supported meetings, and provided a sounding board that fed into continuous improvement, including refined KPIs and stronger specifications for future tenders.
Kevin Clarke, Account Delivery Manager at Procure Plus, said: “What’s made Wave 3 stand out is that Fairhive brought us in as a genuine delivery partner, not just at the procurement stage. Being able to support the team through weekly meetings and act as a sounding board has meant issues get resolved quickly, and it’s helping shape better specs for the next round of tenders too.”
Fairhive’s experience has shown that successful retrofit programmes depend on creating the right conditions for delivery through early procurement, strong internal capacity, and trusted partnerships while using each phase to learn and improve.
As the sector moves towards increasingly ambitious retrofit targets, carrying those lessons forward and building momentum from one programme to the next will be critical to delivering lasting change at scale.
Image credit: Chris Grant/source library.
Procure Plus is a Housing Digital Stakeholder and a social housing regeneration consortium that generates efficiencies by leveraging the procurement of construction materials and contractors.
Read next: ASB Awareness Week 2026: Creating pathways for change
Are you a social housing professional? Sign up for a FREE MEMBERSHIP to upload news stories, post job vacancies, and connect with colleagues on our secure social feed.